December 17, 2018:  Message to Mayor Dick Schramer from Amanda Graham at the Office of Joan Ballweg

I received another update from the DNR regarding the Princeton Dam.  The DNR met with the design team last week and decided the design team needed additional time to complete the necessary bid documents. The target date for bid is now March 5th.  The start of construction will ultimately be determined on water levels, spring runoff impacts and the outcome of the bidding process.  I will continue to provide updates as we get them, and please feel free to contact our office back if you have any specific questions.